A view down one of the wings on the second floor for our new addition.

Construction work on MCS is still moving along.  The second floor to the new addition is nearly completed with the student lockers being installed.  Cabinetry for the classrooms have been installed.  The bathrooms are nearly completed.  The boilers for the addition have been fired up.  The renovation work on the original part of the building is moving along as demolition is nearly completed and wall structures are being put up.  If you drive by you will see the additional spaces for the main office has been enclosed.  We can hardly wait for spring.